Guntur Municipal Corporation planning to complete land acquisition for new Road Over Bridge by Feb. end


Traffic on the Sankar Vilas ROB in Guntur on Saturday.

Traffic on the Sankar Vilas ROB in Guntur on Saturday.
| Photo Credit: T. Vijaya Kumar

Two new Road Over Bridges (ROB) that will be constructed in Guntur are expected to address the growing traffic congestion in the city.

One the projects is the replacement of the Sankar Vilas ROB, which connects the east and west parts of the city. The existing two-lane ROB bears over 60% of the city traffic.

The other is a new ROB on the Inner Ring Road (IRR), which will connect the city with the National Highway and is expected to ease burden on the city’s internal roads.

According to Minister of State for Rural Development and Communications Pemmasani Chandra Sekhar, these two ROBs are essential for the city and would address traffic problems for the next thirty years. Mr. Chandra Sekhar, who represents the Guntur Parliamentary Constituency, said he was able to secure the two railway projects for Guntur city with consistent efforts.

He said that the Ministry of Railways, in a communication on January 8, directed the South Central Railway general manager to complete all prerequisites before inviting tenders for the ROB (the Inner Ring Road one), having an estimated cost of ₹107.79 crore.

The pre-requisites include government consent for closure of level crossing, approval of the General Administration Department, design and land acquisition, if any.

As for the Sankar Vilas ROB, the Union Ministry of Road Transport and Highways approved the project, having an estimated cost of ₹98 crore, in 2024. The government would demolish the old bridge and build a new one in its place.

Speaking to The Hindu, Guntur Municipal Corporation (GMC) Commissioner Puli Srinivasulu said they are trying to complete land acquisition for the Sankar Vilas ROB by February-end and begin construction as soon as possible. He added that they would resolve land-related issues regarding the IRR ROB.

Reacting to the pending works on the Nandivelugu Road ROB, the Commissioner explained that the Railways has already completed constructing a portion of the bridge. The remaining part, however, is supposed to be built by the Roads and Buildings Department, which, however, had been cash-strapped for the past four years. Now, Mr. Chandra Sekhar was trying to get funds from the Centre for the remaining works, he said.



Source link

spot_img

More from this stream

Recomended

Tharpana mandapams at Perur padithurai to be inaugurated on February 10Man ends life in NamakkalUnilever announces plans to establish two manufacturing units in Telanganaपहले पार्ट ने मचाया तहलका, दूसरे-तीसरे की आंधी में उड़ा बॉक्स ऑफिस और अब...Power shutdown in several areas of Tiruchi on January 22 and 23Watch: How is it not rarest of rare case?: Mamata Banerjee slams RG Kar rape and murder sentencingRupee falls 14 paise to close at 86.59 against U.S. dollarSupreme Court asks Delhi Police’s reply on Tahir Hussain’s plea for interim bailSensex crashes 1,235 pts to 7-month low amid massive selling in heavyweight stocksJourney through AM Murali’s surreal metaphysical art in HyderabadDonald Trump inauguration highlights: WHO says ‘regrets’ U.S. decision to withdraw from organisationSri Lankan media spotlights Dissanayake’s ‘balancing act’ with India and China Fire accident in pharma unit at JNPC in Anakapalli district, none injuredPolice suspend Kannada actor Darshan’s gun licenceBengaluru still finds takers for vinyl recordsMLA Munirathna and six others booked for forceful demolition of houses, atrocity against slum dwellers in BengaluruAvanti Fellows’ Akshay Saxena, RCRC’s Ved Arya among Schwab Foundation Awards recipientsIronhill opens newest branch at Bengaluru’s Kanakpura Roadसंजीव कुमार की हीरोइन, जिस पर फिदा थे कई सुपरस्टार, 1977 में एक्ट्रेस ने 1 रोल से चटा दी थी राजेश खन्ना को धूलDemand for NRI representation in Parliament at parliamentary panel meeting